Texas Wesleyan University

    • Fuel Type Natural Gas
    • Application University/School
    • kW Production 800 kW
    • Location Forth Worth, TX, USA

    About This Project

    Texas Wesleyan University launched a $6.2 Million energy-saving project in 2015. The centerpiece of this project is 2G Energy's avus 800, a CHP that provides power to much of the campus spanning 83 acres.

    The natural gas powered CHP plant supplies 80% of power to 80% of campus, while reducing the university's dependency on the public power grid.

    The new power plant also includes a 250-ton absorption chiller, new cooling tower, new heating boilers, pumping systems and central plant optimization controls.

    The project, which was self-funded, will pay for itself in cost savings quickly. The power system is expected to save $377,000 and 5.9 million kilowatt-hours per year.

     

     

     

    Additional Details

    • Total Electrical Power
      800
    • Module
      avus 800c
    Download .PDF

    Project Gallery 4 photos

    • Texas Wesleyan University
    • Texas Wesleyan University
    • Texas Wesleyan University